Shoe development timeline calculator

Most shoe launches run late because of development, not production. Put in the date your shoes need to arrive, and the calculator counts back to the last day you can freeze the sole, start sampling, approve the final sample and place the bulk order.

Fill in testing and transit yourself: ask your lab how long tests take, and your forwarder how long door to door. Sea freight is usually 2–6 weeks, so we start at the long end.

How we count back

  1. Take the transit time off your arrival date. That's when the shoes must leave the factory.
  2. Take off bulk production: 45–60 days in China, 90–120 days in Vietnam. That's when the final sample and the bulk order must be confirmed.
  3. If lab results must be back before bulk starts, take off the testing time too.
  4. Each sample round takes 2–4 weeks, including courier and your review. Most styles are approved in 2–3 rounds.
  5. A new sole mould takes 25–36 days. It has to be ready before the last sample round, so the final sample is made on the real sole. The mould runs alongside upper sampling, but only after the sole design is frozen.

You get two plans: a tight one using the short end of each range, and a safe one using the long end. If the safe plan should already have started, you are at risk. Use materials you already have to save a round, use an existing sole, or move the date.

Where launches usually slip

More than 95% of our orders ship on time. When one is late, it's usually because a supplier delivered materials late, or because an approval sat waiting on the buyer's side. Mistakes in the tech pack come next, since they mean remaking a sample. Give every approval a deadline, so when an answer comes late, everyone can see what it does to the dates.

Check it with us

These are our own numbers as a factory in Quanzhou, not an industry average. See how each stage works on our footwear development page and in the MOQ and lead time guide, or send us your launch date and we'll check it against our real schedule.

💬